While Release 1.0 of the Web Applications System Was Successfully Deployed, Several Factors Contributed to Implementation Delays
Report Information
Date Issued
September 7, 2017
Report Number
2017-20-057
Report Type
Audit
Joint Report
Yes
Participating OIG
Treasury Inspector General for Tax Administration
Agency Wide
Yes (agency-wide)
Questioned Costs
$0
Funds for Better Use
$0
Recommendations
The Chief Information Officer should ensure that all future project management offices are established and operate with an oversight function that is aligned with the organization's governance model and encompasses the project life cycle.